SR 109 Paving, I-5 Work Continue in Aberdeen Area

πŸ”Š Listen Β· narrated by Aiden

On Tuesday, Sept. 8, WSDOT began daytime paving operations on SR 109 at mileposts 33.8 and 37 near Moclips and Taholah, creating temporary traffic stops up to 15 minutes. The work will continue until Dec. 31, 2026, with single-lane alternating traffic in place.

Starting Wednesday, Sept. 9, US 101 between mileposts 28.8 and 67 will have daytime mowing delays from 6:30 a.m. to 4:30 p.m. through Sept. 17. Meanwhile, I-5 lane closures will continue through Sept. 11 in the La Bree Road to Main Street area for weigh-in-motion sensor work, with nighttime closures each night until 3 a.m.

πŸ“„ Source: WSDOT β€” Highway Construction & Closures β€” https://wsdot.wa.gov/travel/road-construction
Source receipts11 of 13 claims supported Β· 85%

Legacy automated check: the original source text was not preserved. These earlier verdicts have not passed the current publication checks and may contain errors. Source: original document β†—

  • βœ“
    WSDOT began daytime paving operations on SR 109 on Tuesday, Sept. 8β€œOn Tuesday, Sept. 8, expect daytime traffic stops up to 15 minutes on SR 109 at milepost 33.8 north of Moclips for paving. Work may be rescheduled if it rains. Temporary traffic lights and single-lane alternating traffic remain in place.”
  • βœ“
    Daytime paving operations on SR 109 are at mileposts 33.8 and 37β€œOn Tuesday, Sept. 8, expect daytime traffic stops up to 15 minutes on SR 109 at milepost 33.8 north of Moclips for paving. Work may be rescheduled if it rains. Temporary traffic lights and single-lane alternating traffic remain in place. Read more on the <a href="https://wsdot.wa.gov/construction-planning/search-projects/sr-109-ocean-city-taholah-remove-fish-barriers">project webpage</a>.”
  • βœ“
    The paving operations on SR 109 are near Moclips and Taholahβ€œOn Tuesday, Sept. 8, expect daytime traffic stops up to 15 minutes on SR 109 at milepost 33.8 north of Moclips for paving. Work may be rescheduled if it rains. Temporary traffic lights and single-lane alternating traffic remain in place. Read more on the <a href="https://wsdot.wa.gov/construction-planning/search-projects/sr-109-ocean-city-taholah-remove-fish-barriers">project webpage</a>.”
  • βœ“
    The paving operations on SR 109 will create temporary traffic stops up to 15 minutesβ€œOn Tuesday, Sept. 8, expect daytime traffic stops up to 15 minutes on SR 109 at milepost 33.8 north of Moclips for paving.”
  • ⚠
    The work on SR 109 will continue until Dec. 31, 2026No usable supporting receipt β€” unverified.
  • βœ“
    Single-lane alternating traffic will be in place on SR 109β€œTemporary traffic lights and single-lane alternating traffic remain in place.”
  • βœ“
    Starting Wednesday, Sept. 9, US 101 will have daytime mowing delaysβ€œWednesday, Sept. 9 through Thursday, Sept. 17: Travelers in both directions of US 101 between the SR 4 interchange (milepost 28.8) and the Grays Harbor County line (milepost 67), will encounter daytime delays from 6:30 a.m. to 4:30 p.m., for mowing along the shoulders of the highway.”
  • βœ“
    Daytime mowing delays on US 101 are between mileposts 28.8 and 67β€œWednesday, Sept. 9 through Thursday, Sept. 17: Travelers in both directions of US 101 between the SR 4 interchange (milepost 28.8) and the Grays Harbor County line (milepost 67), will encounter daytime delays from 6:30 a.m. to 4:30 p.m., for mowing along the shoulders of the highway.”
  • βœ“
    Daytime mowing delays on US 101 will be from 6:30 a.m. to 4:30 p.m.β€œWednesday, Sept. 9 through Thursday, Sept. 17: Travelers in both directions of US 101 between the SR 4 interchange (milepost 28.8) and the Grays Harbor County line (milepost 67), will encounter daytime delays from 6:30 a.m. to 4:30 p.m., for mowing along the shoulders of the highway.”
  • βœ“
    The mowing delays on US 101 will last through Sept. 17β€œWednesday, Sept. 9 through Thursday, Sept. 17: Travelers in both directions of US 101 between the SR 4 interchange (milepost 28.8) and the Grays Harbor County line (milepost 67), will encounter daytime delays from 6:30 a.m. to 4:30 p.m., for mowing along the shoulders of the highway.”
  • βœ“
    I-5 lane closures will continue through Sept. 11 in the La Bree Road to Main Street areaβ€œFrom 8 p.m., Tuesday, Sept. 8 to 3 a.m., Friday, Sept. 11: Up to two lanes of in both directions of I-5 between La Bree Road (milepost 74) and Main Street (milepost 77) will close nightly for weigh-in-motion sensor replacement work.”
  • βœ“
    The lane closures on I-5 are for weigh-in-motion sensor workβ€œFrom 8 p.m., Tuesday, Sept. 8 to 3 a.m., Friday, Sept. 11: Up to two lanes of in both directions of I-5 between La Bree Road (milepost 74) and Main Street (milepost 77) will close nightly for weigh-in-motion sensor replacement work.”
  • ⚠
    Nighttime closures on I-5 will occur each night until 3 a.m.No usable supporting receipt β€” unverified.