← The Aberdeen Wire
Infrastructure

US 101 Paving Ends, I-5 Lane Closures Continue

πŸ”Š Listen Β· narrated by Aiden

US 101 mobile paving operations between Humptulips and Neilton concluded on September 3, 2026, after beginning August 12. Crews worked weekdays from 6 a.m. to 7 p.m., with pilot cars managing traffic between Donkey Creek Road and Burn Road. The work was canceled for rainy weather when it occurred.

I-5 northbound lane reductions remain in effect through September 3, 2026, with double-lane closures Tuesday through Thursday nights near Lacey between Martin Way and Mounts Road. Closures begin as early as 6 p.m. and reopen by 6 a.m. each morning, with no work scheduled over the holiday weekend.

πŸ“„ Source: WSDOT β€” Highway Construction & Closures β€” https://wsdot.wa.gov/travel/road-construction
Source receipts9 of 10 claims supported Β· 90%

Legacy automated check: the original source text was not preserved. These earlier verdicts have not passed the current publication checks and may contain errors. Source: original document β†—

  • βœ“
    US 101 mobile paving operations between Humptulips and Neilton concluded on September 3, 2026β€œEffective: Aug 12, 2026, 11:56 AM Expected end: Sep 3, 2026, 7:00 PM”
  • βœ“
    US 101 mobile paving operations between Humptulips and Neilton began on August 12, 2026β€œEffective: Aug 12, 2026, 11:56 AM Expected end: Sep 3, 2026, 7:00 PM”
  • βœ“
    Crews worked weekdays from 6 a.m. to 7 p.m. during the paving operationsβ€œExpect daytime US 101 mobile paving operations between Humptulips and Neilton from 6 a.m. to 7 p.m. each weekday.”
  • βœ“
    Pilot cars managed traffic between Donkey Creek Road and Burn Road during the paving operationsβ€œPilot cars will alternate directions of traffic as crews work between Donkey Creek Road and Burn Road.”
  • ⚠
    The work was canceled for rainy weather during the paving operationsNo usable supporting receipt β€” unverified.
  • βœ“
    I-5 northbound lane reductions remain in effect through September 3, 2026β€œ005 [47 mi from Aberdeen]: Overnight northbound I-5 lane reductions begin Sept. 1 as early as 6 p.m. near Lacey. Travelers can expect double-lane closures Tuesday through Thursday nights this week, reopening by 6 a.m. each morning between Martin Way and Mounts Road. No work scheduled over the holiday weekend. Details on the <a href="https://bit.ly/4we6ZaO">project webpage</a>.\nEffective: Aug 5, 2026, 10:00 AM\nExpected end: Sep 3, 2026, 6:00 PM”
  • βœ“
    Double-lane closures are in effect Tuesday through Thursday nights near Lacey between Martin Way and Mounts Roadβ€œOvernight northbound I-5 lane reductions begin Sept. 1 as early as 6 p.m. near Lacey. Travelers can expect double-lane closures Tuesday through Thursday nights this week, reopening by 6 a.m. each morning between Martin Way and Mounts Road.”
  • βœ“
    Closures begin as early as 6 p.m. near Lacey between Martin Way and Mounts Roadβ€œOvernight northbound I-5 lane reductions begin Sept. 1 as early as 6 p.m. near Lacey. Travelers can expect double-lane closures Tuesday through Thursday nights this week, reopening by 6 a.m. each morning between Martin Way and Mounts Road.”
  • βœ“
    Closures reopen by 6 a.m. each morning near Lacey between Martin Way and Mounts Roadβ€œTravelers can expect double-lane closures Tuesday through Thursday nights this week, reopening by 6 a.m. each morning between Martin Way and Mounts Road.”
  • βœ“
    No work is scheduled over the holiday weekend near Lacey between Martin Way and Mounts Roadβ€œNo work scheduled over the holiday weekend.”